Zhejiang Petrochemical's 700,000-ton high-pressure polyethylene project has entered the final c

2021-11-15

Recently, some investors asked Rongsheng Petrochemical on the interactive platform: Under the dual-carbon policy, will the second phase of Zhejiang Petrochemical, a holding subsidiary, be put into operation as scheduled? Is the company's electricity consumption situation at the end of 2021 more severe than that at the end of 2020? Rongsheng Petrochemical replied that: the company's current production and operation are all normal, basically not affected by power restrictions. In view of the current power supply situation, the company actively responds to the national energy consumption policy and rationally arranges the production plan. The second phase is currently being put into production gradually, and related work is being actively promoted.


In addition, some netizens raised questions: “After the company’s 40 million tons/year refining and chemical integration project (phase one) is put into operation, the company will announce the full-year production in about 7 months; The related public works equipment has been put into production in November 2020, and 12 months have passed so far, and full production has not yet been announced. What is the reason for the difference in the time between the two phases of the project?", Rongsheng Petrochemical said: Phase II Compared with the first phase, the proportion of chemical products is larger, and the added value of the products is higher. The management of the company and all employees of Zhejiang Petrochemical Company will take safe and stable start-up as the primary task on the basis of running the first phase of the project, and carefully debug during the commissioning process to realize the smooth start-up of the second phase of the project.


u3000u3000 The 700,000-ton/year high-pressure polyethylene project has reached the end of the project


u3000u3000 Since the beginning of November, the Zhejiang Petrochemical Phase II 700,000 tons/year high-pressure polyethylene project undertaken by the Tenth Construction Company of Refining and Chemical Engineering, the project department of the Tenth Construction Company has strengthened process management and control, promoted the construction of the project at full speed, and created favorable conditions for the start-up of the equipment.


u3000u3000 It is understood that the 700,000 tons/year high-pressure polyethylene project consists of two major units, 300,000 tons/year LDPE-EVA and 400,000 tons/year LDPE. Faced with the tight construction period and harsh natural environment, the project department led all the staff involved in the construction to resist typhoons, high temperatures, and sweltering heat, scientifically organized, careful deployment, inverted construction plans, detailed breakdown of remaining engineering quantities, and instrumentation debugging and core Equipment start-up is a key route. Pipeline heat tracing and heat preservation work are inseparable, and go hand in hand to advance the final construction in an all-round way.


u3000u3000 In order to strengthen on-site safety management and control, the project department continues to promote the concept of full participation, full process control, and full management to improve the safety quality of all employees. Attach importance to safety education and training, regularly count new arrivals, and organize safety technical clarifications by various professions and construction managers in various districts to ensure full coverage of the confession. Regularly organize safety emergency drills to improve the ability of construction personnel to avoid and prevent accidents, and improve their vigilance against accidents.


As of November 8, the instrument commissioning, heat preservation, and equipment pipe cleaning of the 300,000 tons/year LDPE-EVA device has been basically completed. The 400,000 tons/year LDPE device instrument commissioning, heat preservation and other work have been efficiently promoted. The entire high-pressure polyethylene The overall control of project construction safety, quality, and progress. Won the first place in the comprehensive evaluation of quality, safety, civilized construction, and progress organized by the owner in October


DISCLAIMER: All information provided by HMEonline is for reference only. None of these views represents the position of HMEonline, and HMEonline makes no guarantee or commitment to it. If you find any works that infringe your intellectual property rights in the article, please contact us and we will modify or delete them in time.